Drivers are advised there is an updated schedule of dates for local City streets to be chip sealed during Citywide Road Resurfacing Project. This is due to weather conditions. The project is underway and continues through mid-November. It is recommended to use alternate routes when possible.
The project includes the removal of existing traffic striping, placing of a chip seal (New Road wearing surface), re-establishment of traffic striping and installation of new traffic loops. The City is contracting Pavement Coating Company to perform this $3 million project funded by Measure A, Gas Tax, and SB-1 Gas Tax dollars.
Having safe, well-maintained roads is a top priority for the City, which knows how important it is to our residents and infrastructure. As one of its Smart City, Safe City programs, the Department of Public Works diligently tracks the Pavement Condition Index (PCI) to assess the condition of streets. Based on available funds, including tax revenue from gas purchases, staff conducts annual assessments and develops road projects.
The following streets that are part of this project are scheduled to be chip sealed as indicated below:
- Betteravia Road from South Broadway to A Street – Friday, 10/3 & Monday 10/6
- Western Avenue from Morrison Avenue to Stowell Road - Monday 10/6
- Bradley Road from Stowell Road to Betteravia Road – Tuesday, 10/7 & Wednesday, 10/8 & Thursday, 10/9
- Cook Street from Miller Street to Broadway – Tuesday, 10/7 & Wednesday, 10/8 & Thursday, 10/9
- Western Avenue from Cook Street to Morrison Avenue – Tuesday, 10/7 & Wednesday, 10/8 & Thursday, 10/9
- Betteravia Road from Miller Street to Highway 101- Friday, 10/10 & Monday, 10/13 & Tuesday, 10/14
- Alvin Avenue from Blosser Road to Curryer Street – Friday, 10/10 & Monday, 10/13 &Tuesday, 10/14